某坡地高層建筑常用基礎(chǔ)方案比選
李釗1,劉庭金1,2,夏文宇1
摘 要

1 華南理工大學(xué)土木與交通學(xué)院,廣州 510640;2 華南理工大學(xué)亞熱帶建筑科學(xué)國家重點(diǎn)實(shí)驗(yàn)室,廣州 510640

 

[摘要]  以某工程實(shí)例的地基基礎(chǔ)設(shè)計(jì)為背景,分析了在坡地地層起伏且基巖上部可壓縮層厚度不均條件下,CFG樁復(fù)合地基基礎(chǔ)、筏板基礎(chǔ)以及樁基基礎(chǔ)的適用性與經(jīng)濟(jì)性,并將這三種常用基礎(chǔ)設(shè)計(jì)方案進(jìn)行了對比分析。結(jié)果表明:在坡地地層起伏、基巖上部可壓縮層厚度不均、場地存在孤石等不良地質(zhì)條件下,CFG樁復(fù)合地基基礎(chǔ)較難控制建筑物的最大沉降量和整體傾斜量;筏板基礎(chǔ)能消除場地孤石對施工的影響,但在控制建筑物的最大沉降量和整體傾斜量方面不經(jīng)濟(jì);樁基在控制沉降方面具有優(yōu)勢,且嵌巖樁樁端的抗剪切作用能大大降低基礎(chǔ)在基巖分界面存在滑動的潛在風(fēng)險(xiǎn),在施工時(shí)能降低遇到孤石的可能性,滿足可行性和經(jīng)濟(jì)性要求。

 

[關(guān)鍵詞]  坡地;孤石;CFG樁;筏基;樁基;基礎(chǔ)比選

 

中圖分類號:TU472              文獻(xiàn)標(biāo)識碼:A          文章編號:

 

作者簡介:李釗,碩士研究生,Email: muzilizhao@126.com

 

A high-rise building’s common foundation schemes comparison and selection in a sloping fields

Li Zhao1, Liu Tingjin1, 2,Xia Wenyu1

1 School of Civil Engineering and Transportation, South China University of Technology, Guangzhou 510640, China; 2 State Key Laboratory of Subtropical Architecture Science, South China University of Technology, Guangzhou 510640, China

 

Abstract: In the background of a foundation design of an engineering example, the applicability and economy of CFG

pile composite foundation, raft foundation and pile foundation were analyzed under the condition of the rock ups and downs and thickness inequality of compressible soil in upper rock in a sloping slope, and the three schemes of foundation design were contrasted and analyzed. The results show that in the conditions of rock ups and downs and thickness inequality of compressible soil in upper rock and boulder, the raft foundation is difficult to control the building’s biggest settlement and the tilting quantity, which is the same with CFG piles composite foundation in a low price, but it can eliminate the influence of boulder in the construction. Rock-socketed pile end shearing action can greatly reduce the foundation in the bedrock interface slip of potential risk, and it can reduce the possibility of boulder met in the pile foundation construction, which achieve applicability and economy for a project.

 

Keywords: sloping field; boulder; CFG piles; raft foundation; pile foundation; foundation comparison and selection

 

      獻(xiàn)

[1] 龔曉南. 復(fù)合地基理論及工程應(yīng)用[M]. 北京:中國建筑工業(yè)出版社,2002.

[2] 付冬平. 廣州北部孤石的特征及其工程特性[J]. 廣東土木與建筑,20096:2133.

[3] 劉光壽. 某工程基樁質(zhì)量事故巖土工程勘察原因分析[J]. 廣東土木與建筑,20092:4648.

[4] JGJ792002建筑地基處理技術(shù)規(guī)范[S]. 北京:中國建筑工業(yè)出版社,2002.

[5] GB500072002建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范[S]. 北京:中國建筑工業(yè)出版社,2002.

[6] 趙明華,曹文貴,何鵬祥,. 巖溶及采空區(qū)橋梁樁基樁端巖層安全厚度研究[J]. 巖土力學(xué),2004,25(1):6468.

 

[7] JGJ942008建筑樁基技術(shù)規(guī)范[S]. 北京:中國建筑工業(yè)出版社,2008.